Stop the Amazon Data Center Campus in Falls Township

Our Mission

Protect our children, community, and environment from the harms of the massive Amazon data centers.

Falls Township Data Centers

Amazon is creating a massive (3M+ sq. ft.), 11-data-center campus in Falls Township at the Keystone Trade Center.​

Fast Facts

Size: 3M+ sq. ft.

​

Power Required:​ 600 MW

​

Water Use: Unknown

​

Noise: Unknown, no limits

 

(Township lifted noise restrictions for data center sites at this location)

​

Location: Falls Township, PA, Keystone Trade Center

​

Developer: NorthPoint Development

​

Operator: Amazon Web Services

​

​

​

Records

​​​​Members of the Falls Township Data Center Resistance have been filing Right to Know and other records requests. We’re sharing what we’ve obtained here.

​​

PA Department of Environmental Quality

 

Amazon’s Air Quality Permit Application​ (most recent 09-0261a)

 

PA DEP Permit Approval for Initial Minor Synthetic Source Air Quality Permit Modification (November 2025)

 

May 6, 2026, Facility Incident Report

​

​​

Falls Township​

​

December 2025 Signed Non-Disclosure Agreement

​​

Resolution Approving  Building 6 (1M Sq. Ft. Building) for Data Center

​

Resolution Approving the 10 Additional Data Center Buildings

​

Various Comments and Letters 1 

​

Various Comments and Letters 2

​

March 26, 2025 letter from Morrisville Municipal Authority (MMA)

​

2025 Professional Services Agreement

​

Memorandum of Understanding (MOU) 

​

Building Permits

​

2021 Custom Soil Resource Report for Bucks County, PA and Burlington Co., NJ

​

Erosion & Sedimentation Control (E&S) Narrative - KTC - Phase 2

​

Erosion & Sedimentation Control (E&S) Narrative - KTC - Area 3 Development

​

Post Construction Stormwater Management (PCSM) Narrative - KTC - Phase 2

​

Post Construction Stormwater Management (PCSM) Narrative - KTC - Phase 3

​

January 2025 Waiver Requests

​

Appears to be Elements of Land Development and Subdivision Application

 

​

1,800+ pages of documents, including erosion and settlement control information and township issued permits through most of June 2026. Township released these records in response to request for all records on the “Amazon Data Center at the Keystone Trade Center."

​​

 

Delaware River Basin Commission (DRBC)

 

Delaware River water withdrawals from the former U.S. Steel (USX) site from 1987 to 2025. At its peak usage in the records (1988) U.S. Steel was taking 70.99 billion gallons of water from the Delaware River. In 2025, the site withdrew 432 million gallons of surface water.

​​

DRBC’s authorization for water withdrawals from the Delaware River for the former USX, current Morrisville Municipal Authority facility​

Important Dates

No events at the moment

Timeline

December 7, 2020

 

​Northpoint Development Presents Site Master Plan​

​

Falls Township Board of Supervisors discusses Keystone Trade Center plan and approval processes.

​

​​

​

August 13, 2024​

 

Zoning Hearing Board Approves Data Center Noise Variance

Zoning Board approved the exemption of restrictions at the property line for data center use on two parcels.

 

​

​

November 25, 2024

 

Board of Supervisors Approves NDA

Board approved NDA, incuding notifying client of Right to Know Requests and "anything [the township] has to do to defend it, [the developer] will pick up the cost."

 

​

​

​

February 24, 2025

​​​

Planning Commission Approves Developer Change from Warehouse to Data Center End Use 

Key meeting for Planning Commission approval of Phase 2 of KTC, switching from a 1M sq. ft. building from warehouse to data center use, and switching Phase 3 of the Keystone Trade Center project to a planned data infrastructure campus.

 

​

​

March 24, 2025

 

Board Approves Data Center Proposals

The Board of Supervisors approves amending previous approval for a  1M sq. ft. warehouse for data center use instead, as well as changing 3 M sq. ft. of warehouse space across 4 buildings to 10 main buildings on 247 acres for a "data infrastructure campus." The township and developers have not clarified if these are 10 additional data center buildings or supporting equipment for the 1M sq. ft. facility. However, the low-resolution drawings of the second site look similar to images of other planned data center campuses with multiple clustered data centers.

​

​​​​

​

​

June 9, 2025

 

Amazon Announces Data Center Plan

Amazon and Township make data center announcement.

 

​

 

June 10, 2025

 

Falls Township Environmental Advisory Commission Notes Air Quality Permits for 72 Diesel Generators

The Department of Environmental Protection invited comments in June on an Air Quality Plan Approval Permit covering the

installation of 72 - 2.5 MW diesel-fired emergency generators (180 MW total) and two 750 kW diesel-fired house emergency generator engines at the new Amazon Data Services Inc. data center in Falls Township, Bucks County.

 

​

 

August 14, 2025

 

Falls Township Environmental Advisory Commission Votes to Send Data Center Draft Ordinance to Board of Supervisors

EAC voted to send the PennFuture model data center ordinance to the Supervisors with the suggestion that a joint committee be formed with members from the EAC, Planning, and Zoning to refine an ordinance specific to Falls Township.

​

​

​​

​

October 14, 2025

 

The Regional Electric Grid (PJM) Independent Market Monitor Raises Concerns About Deal Between PECO and Amazon

"...the Market Monitor recommends that the TSA  not be approved unless PECO can demonstrate that the referenced new data center load can be served reliably and without imposing increased capacity costs and energy costs on all

PJM customers."

 

​

​

November 21, 2025​

 

Federal Regulators (FERC) Approve the PECO-Amazon Agreement

 

​

 